CHAPTER 8: UNDERGROUND SERVICES
(GENERAL SERVICE AND MULTI-UNIT RESIDENTIAL)
8.01 GENERAL
8.02 CONNECTIONS
8.03 CLEARANCES
8.04 UNDERGROUND SERVICE TO METER SOCKET
8.05 FREE-STANDING SUPPORT FOR UNDERGROUND SERVICE ENTRANCE
8.06 UNDERGROUND SERVICE TO CT CABINET
8.07 UNDERGROUND SECONDARY SERVICE, SERVED FROM OVERHEAD
- LIMITATIONS – DISTANCE
- LIMITATIONS – SIZE
8.08 PADMOUNT TRANSFORMER SERVICE PRIMARY CONDUIT & CONDUCTORS
- TRANSFORMER SLABS
SINGLE PHASE
THREE PHASE, 1000KVA & SMALLER
THREE PHASE, 1500KVA & LARGER
- SLAB INSPECTIONS
- SECONDARY CONDUITS & CABLES
- METERING ON PADMOUNTED TRANSFORMER
- GENERAL PADMOUNT REQUIREMENTS
8.09 THREE PHASE PADMOUNT TRANSFOMRER WITH SEPARATE SECONDARY COMPARTMENT
- ADD TO AN EXISTING SLAB
- SERVICE CONDUCTORS
- INSTRUMENT TRANSFOMRER METER ON TRANSFORMER
|