February 2013
NRC Issues Revised Confirmatory Action Letter for FCS - 02/26/13
January 2013
Nuclear Regulatory Commission Receive Details on Fort Calhoun Station Recovery - 01/08/13
November 2012
OPPD Highlights Fort Calhoun Station Progress at Public Meeting - 11/15/12
September 2012
Nuclear Regulatory Commission held meeting with OPPD in Blair - 9/12/12
July 2012
Public Dialogue on Fort Calhoun Continues - 7/17/12
June 2012
OPPD Moving in Right Direction - 6/11/12
May 2012
NRC Open House / OPPD Open House - 5/31/12
April 2012
FCS Operations Training Accreditation Renewed - 4/18/12
NRC Public Meeting Held - 4/04/12
March 2012
Finding Was Expected; FCS Making Progress - 3/12/12
New Meteorological Equipment - 3/12/12
NRC Examining Potential Impact on Nuclear Plant Safety from Upstream Dam Failure - 3/6/12
Building New Equipment - 3/04/12
February 2012
NRC Holds Second Public Meeting with OPPD - 2/22/12
OPPD Bringing in Industry Experts to Assist with Recovery Effort - 2/22/12
January 2012
NRC, OPPD Discuss New Process - 1/19/12
Local Journalists Tour Fort Calhoun Station - 1/18/12
December 2011
Fort Calhoun Station Enters New Category - 12/13/11
NRC Issues Revised Confirmatory Action Letter for FCS
February 26, 2013
The Nuclear Regulatory Commission (NRC) issued a revised Confirmatory Action Letter or CAL to OPPD on February 26, 2013, that adds three items to the Fort Calhoun Station (FCS) restart checklist the NRC had issued on June 11, 2012. Those items include some performance failures in the safety system, items involving qualifications for electrical penetrations in containment, and some internal structures inside containment. OPPD has agreed to meet these conditions prior to restart.
OPPD has been aware of all of the items in the new CAL and has been working on them for months. Significant progress has been made with NRC inspections well underway. The NRC inspections and the extensive work will add value to help bring Fort Calhoun back to a high performing plant.
Return to Top
Nuclear Regulatory Commission Receive Details on Fort Calhoun Station Recovery
January 8, 2013
The key message that OPPD has made significant progress at Fort Calhoun Station (FCS) was well-received by the Nuclear Regulatory Commission (NRC) chairman and commissioners at the January 8th NRC meeting in Rockville, Md.
OPPD representatives told the commissioners that the work being done at FCS is designed to take the plant beyond safe restart and enable it to safely operate more effectively and efficiently well into the future.
The commissioners also thanked OPPD for its transparency throughout the NRC’s Inspection Manual Chapter 0350 process, and for OPPD’s willingness to bring in outside help to return FCS to operational excellence. View the complete presentation.
Return to Top
OPPD Highlights Fort Calhoun Station Progress at Public Meeting
November 15, 2012
OPPD met with the Nuclear Regulatory Commission (NRC) at a public meeting on November 15 at the former Dana College in Blair. OPPD presented the progress it had made on its commitments for restarting the plant, plans for sustained improvement, for independent assessments and other information. After the formal presentations, the NRC opened the meeting for public comments and questions. View the complete presentation.
Return to Top
Nuclear Regulatory Commission held meeting with OPPD in Blair
September 12, 2012
The public had the opportunity on September 11 to review work underway at the Fort Calhoun Station (FCS) and efforts to prepare it for restart. OPPD and the Nuclear Regulatory Commission (NRC) recounted the status of performance improvement items outlined in a Confirmatory Action Letter the NRC sent to OPPD on June 11. Major accomplishments included establishing a dedicated work management control center and the safe removal of fuel from the reactor. Other items discussed during the meeting included bringing in industry-leading Exelon Nuclear to operate FCS. View the complete presentation for a comprehensive overview. The next NRC public meeting will be November 15, 6-9 p.m., and will be held at Dana College Gardner-Hawks Center, 2848 College Drive, Blair, Nebraska.
Return to Top
Public Dialogue on Fort Calhoun Continues
July 17, 2012
The public had the opportunity on July 17 to track progress OPPD is making toward bringing Fort Calhoun Station (FCS) on line. One major change that is taking place is in the “culture” at FCS. Plant Manager Mike Prospero highlighted FCS employees’ marked improvement in industrial safety and human performance, both sitewide and at the department level. He also cited several examples of physical work accomplished at the plant.
Mr. Prospero’s comments came during a public meeting held by the Nuclear Regulatory Commission (NRC) in downtown Omaha.
Vice President and Chief Nuclear Officer Dave Bannister made the key point that Omaha Public Power District will not restart FCS until it is convinced that OPPD is ready to operate FCS at a high level of performance, and when the Nuclear Regulatory Commission concurs with that.
While OPPD’s formal presentation to the NRC was factual and straightforward, the passion and personal commitment about getting FCS back on track was evident from Mr. Bannister, Mr. Mike Prospero and FCS Recovery Manager Ron Short.
For his part of the OPPD presentation, Mr. Short provided a high-level overview of progress in each of the six areas that make up the IPIP.
The NRC discussed the Confirmatory Action Letter and Restart Checklist it has issued to OPPD and its efforts in conducting the numerous necessary inspections at FCS.
During the two hours allotted to public comments and questions posed to both organizations, the topics ranged from last year’s flooding to dry-cask storage of spent fuel at FCS.
Return to Top
OPPD Moving in Right Direction; Receives Confirmatory Action Letter & Restart Check List for Fort Calhoun Station
The Omaha Public Power District continues to make good progress in implementing its comprehensive Integrated Performance Improvement Plan (IPIP) to restart Fort Calhoun Station since it rolled out the plan to the public in February at the NRC public meeting.
As part of the Nuclear Regulatory Commission’s (NRC) process, the NRC issued a Confirmatory Action Letter (CAL) with an attached Restart Checklist on June 11, 2012. Those documents can be found here.
The NRC letter confirms that OPPD is working on the appropriate issues at the plant, and it formalizes the commitments that the company has made to address all of the issues that led to the NRC placing FCS into Chapter 0350, a special category calling for additional NRC oversight for plants in extended shutdown. Most of the work necessary to complete these commitments is underway or has already been completed.
While some things remain unknown, such as the scheduling of upcoming NRC inspections and any items that may arise during discovery, OPPD continues to thoroughly and aggressively work the plan and is committed to restarting the plant according to the current schedule.
Fort Calhoun Station has been safely shut down for a refueling outage since April 2011.
Return to Top
NRC Open House May 31
May 31, 2012
The Nuclear Regulatory Commission (NRC) hosted an informal open house on Thursday, May 31, at the Doubletree Hotel in downtown Omaha from 11 a.m. to 2 p.m. This was the latest in the NRC’s public meetings on Fort Calhoun Station. The event enabled the public to talk one-on-one with NRC region representatives about Fort Calhoun Station and NRC policies.
OPPD Open House
May 31, 2012
Simultaneously, OPPD hosted a similar open house nearby. Members of the general public and reporters asked questions of OPPD about Fort Calhoun Station, and basic principles of nuclear power. OPPD representatives also were on hand to discuss the district’s advances in renewable energy, environmental stewardship and energy efficiency.
Return to Top
FCS Operations Training Accreditation Renewed
April 18, 2012
On April 18, 2012, the Institute of Nuclear Power Operations’ (INPO) National Academy for Nuclear Training accreditation board renewed the accreditation of Fort Calhoun Station’s (FCS) operations training programs. As per its procedures, INPO convened a five-member board that included a representative from the Nuclear Regulatory Commission, personnel from two other nuclear utilities and two non-nuclear training experts. This board conducted a thorough review to ensure FCS meets all of INPO’s criteria for this critically important training.
Return to Top
NRC Public Meeting Held
April 4, 2012
OPPD met with the NRC on April 4 in Blair for another of a series of regular public meetings that are part of the special NRC oversight process. OPPD managers briefed the NRC on progress being made toward improving the plant’s performance. OPPD leaders also assured the NRC that the plant is prepared for any flooding that may arise during the 2012 flood season.
The NRC said it will release a checklist by the end of April on all the tasks OPPD will have to accomplish at Fort Calhoun Station before it is allowed to restart.
OPPD managers also communicated to the NRC about equipment on site that has been repaired or replaced, such as the station’s meteorological tower and the switchgear that was damaged in a fire last June. They also went into detail on the plant’s Integrated Performance Improvement Plan.
The meetings are between OPPD and the NRC and are open to the public, allowing a firsthand look at the information being exchanged between the two organizations.
Return to Top
Finding Was Expected; FCS Making Progress
March 12, 2012
In an inspection report made public on its website on March 12, 2012, the Nuclear Regulatory Commission stated what OPPD had expected: Fort Calhoun Station would receive a preliminary red finding related to an event on June 7, 2011. On that date, an electrical fault resulted in a fire in one of the two switchgear rooms at the plant. The plant’s fire suppression equipment deployed quickly and extinguished the fire within an hour. The plant was in cold shutdown at the time. At no time was the public’s health and safety endangered.
The NRC performed a special inspection on the event and concluded the safety-related 480-volt electrical distribution system design requirements were not properly maintained through maintenance, modifications and design activities. These deficiencies resulted in the failure of the switchgear.
OPPD already has completed much of the work necessary to address the NRC’s concerns related to this event. See below.
Red denotes a finding of high safety significance in the NRC’s Reactor Oversight Process. This finding will be added to the recovery list that will be addressed in the FCS Integrated Performance Improvement Plan.
Return to Top
New Meteorological Equipment
March 12, 2012
Another step toward recovery took place in the first full week of March when workers restored the site’s meteorological tower. While the tower structure survived the flooding, flood waters knocked out all the equipment and electrical components on the ground. While the tower was out, Fort Calhoun would have used data from the nearby Blair, NE, tower if necessary.
Return to Top
NRC Examining Potential Impact on Nuclear Plant Safety from Upstream Dam Failure
March 6, 2012
On March 6, 2012, the Nuclear Regulatory Commission announced it has started a formal evaluation of potential safety implications for dam failures upstream of U.S. commercial nuclear power plants. The NRC recently completed an initial screening assessment and, while this screening did not identify any immediate safety concerns, has recommended further evaluation.
OPPD workers successfully protected Fort Calhoun Station from unprecedented floodwaters in the summer of 2011 and have been called on to share their expertise by others in the nuclear industry. Fort Calhoun Station was designed to withstand up to 1.2 million cubic feet of water per second flowing by the plant in the river. That scenario includes a dam breaking upstream. At the height of the flooding, the amount of water flowing by was about one-sixth that amount.
Return to Top
Building New Equipment
March 4, 2012
On March 4, 2012, personnel at FCS successfully energized the equipment that replaces the damaged bus for testing. This is a major milestone in the recovery process as the bus is necessary to complete the refueling outage that was interrupted last May by the flooding. Testing on this equipment continues.
To address issues on connections inside the equipment, OPPD added silver plating to the connections to ensure low-resistance connections in the bus bar and on similar equipment.
In the design review and work-planning area, we are changing the way we operate. We also will be pressing vendors supplying products and services affecting safety-related equipment to ensure that similar occurrences are avoided in the future.
We are redesigning our electrical system to provide additional isolation of the equipment so that a problem in one system does not spread into the backup system.
Return to Top
NRC Holds Second Public Meeting with OPPD
February 22, 2012
OPPD officials met with the NRC commissioners in a public meeting on Feb. 22, 2012, at NRC headquarters in Rockville, Md. The NRC streamed a webcast of the meeting through its website, nrc.gov.
This was the second in a series of public meetings the NRC is holding as part of its Inspection Manual Chapter 0350 oversight process for OPPD’s Fort Calhoun Station.
Chapter 0350 is a special category of the NRC’s inspection manual for nuclear plants that are in extended shutdowns with performance issues. The process gives the NRC the flexibility to address multiple issues and provides more structure around plant-restart.
Return to Top
OPPD Bringing in Industry Experts to Assist with Recovery Effort
February 22, 2012
OPPD is taking aggressive, in-depth measures to manage the current status of the plant by bringing in the assistance of other high-performing power plants and industry experts to serve as independent third-party resources.
For example, OPPD is contracting with Exelon Nuclear Partners to help lead the recovery efforts and to establish and sustain a top level of operating performance. A blended team of Exelon and OPPD employees is coordinating the recovery effort.
The largest operator of nuclear plants in the U.S., Exelon operates some of the top-performing plants in the country. This arrangement is not about Exelon taking over direct operation of the station or purchasing the station. It is about providing experienced assistance in the recovery of the station.
In addition, experts from the Institute of Nuclear Power Operations (INPO) are helping Fort Calhoun Station identify actions needed to achieve sustainable, improved performance.
Established by the nuclear power industry in 1979, INPO is a nonprofit organization based in Atlanta, whose mission is to promote the highest levels of safety and reliability at nuclear power plants.
All of these efforts support OPPD’s mission to safely provide our customers with reliable electricity at a reasonable cost.
Return to Top
NRC, OPPD Discuss New Process
January 19, 2012
Omaha Public Power District officials met with U.S. Nuclear Regulatory Commission (NRC) staff in a public meeting January 19, 2012, in Omaha. NRC staff discussed specifics of the process, known as Inspection Manual Chapter 0350, which it will use to maintain oversight of Fort Calhoun Station.
OPPD emphasized that nuclear safety remains the plant’s top priority as it works to complete a lengthy list of tasks before it can restart the plant. It also told the independent nuclear regulator that is working to correct issues identified by the NRC.
The NRC notified OPPD it would be going into this category of regulation on December 13, 2011.
As part of the process, the NRC will hold regular meetings with OPPD that will be open to the public. The NRC also will be devoting a special area of its website to allow the public to follow the process.
View video of the NRC and OPPD presentations.
Return to Top
Local Journalists Tour Fort Calhoun Station
January 18, 2012
Sixteen area journalists toured Fort Calhoun Station on January 18, 2012, to document progress made in cleaning up the damage from the flooding of summer 2011. President and Chief Executive Officer Gary Gates and Vice President and Chief Nuclear Officer Dave Bannister discussed the current plant condition and what is being done to correct issues identified by the Nuclear Regulatory Commission (NRC), the independent regulator of the nuclear industry.
The tour walked media through areas that last summer were filled several feet deep with currents of the Missouri River flowing through the site. Fort Calhoun had been safely shut down for routine refueling and maintenance when record rains and deep snowpack in the Missouri River basin brought the flood waters on site in June. The plant remained in safe shutdown throughout the summer and remains shut down while a number of tasks are being completed to make certain it will be safe to restart it and begin generating electricity.
A number of tasks remain to be completed before OPPD is convinced it is safe to restart the plant and the NRC gives its permission to do so.
To view the entire press conference, click here.
Return to Top
Fort Calhoun Station Enters New Category
December 13, 2011
Fort Calhoun Station remains safely shut down following last summer’s flooding. On December 13, 2011, OPPD learned that the Nuclear Regulatory Commission (NRC) has placed Fort Calhoun Station into a special category referred to as Manual Chapter 0350.
This category is designed for plants that are in extended shutdowns and provides the NRC with the flexibility to address multiple issues and more structure around plant restart.
The move will mean additional oversight for OPPD as it corrects issues at the plant previously identified and completes its extensive preparations for restarting the plant following last summer’s flooding. The flooding also prevented the NRC from conducting its normal baseline inspections, which must be completed. Current estimates put the plant restart at some time in the second quarter, subject to regulatory approval.
OPPD is committed to doing whatever necessary to see that Fort Calhoun Station returns to high-performing plant status with safety, as always, our first priority. We will continue to work with the NRC to achieve these goals.
Return to Top
|